When calendar or shift information is changed, activity planned start date and hour and the planned duration are assumed fixed and system re-schedules. To do so, the Project must be saved first, and then Re-plan option located in F9 – right click menu must be selected.
When previous activities are changed, and activity is saved, activity start date is re-calculated according to the planning procedures and planned records are updated after re-planning.
When resources are changed, and Resources window is closed, activity start date and hour are re-planned assuming that planned duration is fixed.
When materials are changed, and Materials window is closed, the related materials' planned quantities in Warehouse Totals are updated.
When work parameters are changed, planned start and end dates are assumed fixed and work duration in-between is re-calculated. This change applies to the planned duration of the project.

When status info is Approved:
When status is Approved, you cannot make changes in General Info and Previous Activities tabs. You can only add and record materials of Input and Output types in Attached Records menu > Materials window.
You can also make resource entry and record planned resource usages in Resources window.

When status info is Started:
When status is Started, you can change Actual Date and Duration information in Activity window > General Info tab.
You can only add and change materials of Input and Output types in Attached Records menu > Materials window. However, the following rules apply to change materials.

...