The actual resource usage in the operations of the production order is recorded using Actual Resource Usage Entry option located in the right mouse button menu.
Actual Resource Usage Entry option is located in the right mouse button menu of the production orders of which Status is Work in Process, Stopped or Completed. Actual resource usage entry cannot be performed for work orders of which the status is Not Started or Closed.
The actual resource usage entry window can be used to record the resource usage information for a specific date range or on a daily basis.
If the resource usage is recorded for a specific date range, the Start Date, Start Time, End Date and End Time fields must be filled in. The LOGO application generates daily records for the specified range. The employee's department workdays and daily work hours, and the daily work hours of the workstation are processed for daily record generation.
First, the suitable days for the department of the employee in the given date ranges are determined. Then the actual start time and actual end time of the resource are determined for the identified days. If the generation date of the schedule is the first day of the date range, the actual start time is the time specified by the user. The end date is determined by checking the daily working hours of the workstation.
If the daily work hours of the employee were longer than the work hours of the workstation, the employee would have completed his daily work once the daily working hours of the workstation are completed.
If the daily work hours of the employee were shorter than or equal to the work hours of the workstation, the employee would have completed his daily work once the daily working hours are completed.
If the generation date of the schedule is the last day of the date range, the checks are performed according to the end time specified by the user.
If the employee's daily work hours > end time, the employee cannot complete the work at the end time.
If the employee's daily work hours <= end time, the employee would have completed the work at the end of his daily working hours.
When resource usage is recorded for a single day, the record is generated according to the start time and end time to be applied for this specific date only. However, no checks are performed for such records; the Date, Start Time, End Time and Time information is recorded as is.