A project's progress payments are calculated over a Construction Diary and BoQ in construction sector. Bill of Quantities (BoQ) is kept to determine the completion rate of the works done within the scope of activities and it is prepared to perform measuring calculations of the production in the relevant progress payment period. Total production quantities are calculated with measurements that are provided in Bills of Quantities in detail.
If System Settings > Project Management > Defaults and Parameters > "In Calculation of Progress Payment Production Totals" parameter value is set to Use Quantity Info, production total is calculated based on the measuring information given under the Construction Diary and BoQ tab. Thereby total production amount is calculated on activity basis. Production amount is multiplied by the unit price of the contract transaction that has been linked to the activity, and the result gives the production total. Progress payment production total is used in calculating contract deductions and billing progress payments.

Construction Diary

You can enter in Construction Diary pane only if you specify Project Code and Contract Number in the related fields. Contract transactions that are linked to the activity/activities are selected in Construction Diary lines.

Item No

The code of activity. It opens Project Activities browser. You can select multiple activities. Project Activities browser lists the activities that match with the project and contract information designated in the Progress Payment window and that are in any status apart from Draft and Approved. You can select from sub-activities only. After selecting the sub-activity, the related parent activity is transferred to the Construction Diary field.

Description

It is the description of the activity. You access Project Activities browser from the field to select the related activity. It allows multiple selection.

Type

After selecting a Contract, unit information that has been designated in line is transferred to the field automatically.

Code

After selecting a Contract, material / service code that has been designated in line is transferred to the field automatically. It can be changed if required.
Code field opens Activity Contract Info Connections browser. This browser lists the transactions of the contract that is linked to the activity and is selected in progress payment form. After selecting contract transaction from the list, line type, material / service code and description and unit information of the selected contract is shown automatically in the corresponding fields. BoQ (Bill of Quantities) information is entered based on this activity and contract line. Note that you cannot enter in BoQ lines for an activity line if it is not linked to a contract.

Description

After selecting a Contract, material / service description in contract line is transferred to the field automatically. It can be changed if required.

Contract Quantity

After selecting the contract, contract quantity is shown in the field automatically. System Settings > Project Management Parameters > Contract quantity exceedance control in Construction Diary parameter controls if the total production quantity in Progress Payment > Construction Diary lines exceeds the quantity in the related contract transactions.

Unit

After selecting the Activity definition, activity's unit information is transferred to the field automatically and it cannot be changed.

Previous Progress Payment Production Quantity

Activity's total quantity information from the previous progress payments is transferred to the field and it cannot be changed.

Current Progress Payment Production Quantity

It is the total of lines entered in BoQ for the activity line. This field does not give the totals of sub-activities for a parent activity line since sub-activities may have different units.

Total Production Quantity

It is the total of the previous progress payment production quantity and the current progress payment production quantity.

Bill of Quantities (BoQ)

This field is used to enter quantity information for the selected sub-activity line in Construction Diary section. Use Insert key to add a line. You can enter information in BoQ for sub-activities of the lowest level only. Therefore, only if the line that is selected in Construction Diary section is a sub-activity, you can enter data in BoQ. When the Construction Diary line is deleted, the related BoQ line is deleted as well. When BoQ lines are updated, Construction Diary lines are recalculated.

You cannot make an entry in BoQ section unless a contract is linked to the Construction Diary lines.

Description

It is the description of the BoQ line.

Quantity / Width / Length / Height

Quantity, width, length and height information of the works done within the scope of the sub-activity is entered in these fields. Both integer and decimal values can be entered. You can also enter a negative value for the Quantity info.

Total

The total field value is calculated automatically by multiplying quantity, width, length and height values.