MRP Net Change option is located under the Production Planning menu of the Planning program module in case the used LOGO application has Net Change feature.

In order to run Net Change, the feature has to be activated by using "MRP Net Change – Open" parameter located in the planning parameters of the System Administration section.

When MRP Net Change is selected, recorded Material Requirements Planning (MRP) records are listed. The record is selected that the net change will be applied to. Net change cannot be run over Material Requirements Plans triggered by MPS proposals.

Filter option located in the right mouse button menu is used to specify conditions for net change.



The filter options and functions of the MRP Net Change window are:

Filter

Value

Schedule Start Date

Start / End

Material (Class) Type

Commercial Good / Mixed Case / Deposited Item / Raw Material / Semi Finished Good / Finished Good / Material Class (General) / Material Class (With table)

Material (Class) Code

Group / Range

Material (Class) Description

Group / Range

Material (Class) Aux. Code

Group / Range

Material (Class) Auth. Code

Group / Range

Material (Class) Group Code

Group / Range

Material (Class) Vendor Code

Group / Range

Material Class Characteristics

Characteristic 1-10

Order Date

Group / Range

Order Number

Group / Range

Order Aux. Code

Group / Range

Order Auth. Code

Group / Range

Order Slip Doc. Number

Group / Range

AR/AP Code

Group / Range

AR/AP Description

Group / Range

AR/AP Aux. Code

Group / Range


Once the conditions are set, transactions are listed by clicking on "OK" button. The transaction result containing changes of main production plan is displayed on screen. The changes are updated by "Calculate" option.

Because there will be changing requirements for the materials subjected to Net Change, the proposals generated after MRP have to be updated.

If proposal line info of the materials has not changed, these lines are updated by new values. If there are new requirements belong to different delivery dates, new lines are added to same proposal slip.

If there are delivered lines, "While deleting MPS/MRP/CTP if there is a transaction with unchanged status" (break relations / slips will be deleted) parameter is considered. If "slips will be deleted" option is selected, related material lines are deleted in delivery slip. If only this material is take place in slip lines, the slip is deleted too. If "break relations" is selected, the slip line relations are broken for the materials.

However, the slips of which status info has been changed are not updated. If the change in plan increases the requirements, a new slip is generated for the missing amount.